Answer:
The army contract
Explanation:
Productivity can be measured by output per hour. i.e.
dividing the total output by hours worked.
productivity = output/hours worked
The navy contract
output =4,300
the hours worked = 20 workers working for two weeks, each week has 40 hours
Each worker worked 40 x 2 hours = 80 hours
20 workers worked for
80 hrs x 20
= 1600 hours
Productivity = 4,300/1600
=2.6875
For the military contract
output = 8300
hours worked
= 25 workers in three weeks, each week 40 hours
each worker worked, 40 x 3 hours = 120 hours
Twenty-five workers:
=25 x 120 hours
= 3000 hours
Productivity = 8300/3000
=2.766
The productivity for the military contract (2.766) was higher than for the navy contrac t(2.6875).