Answer:
270 units
Explanation:
Given that,
Ordered placed for product M = 110 units
Number of units of product M on hand = 30 units
Each M requires = 4 units of Component N
Number of units of component N on hand = 50 units
Required product M:
= Ordered placed for product M - Number of units of product M on hand
= 110 - 30
= 80 units
Total requirement for component N:
= Required product × Requirement for each M
= 80 units × 4 units of Component N
= 320 units
Net requirements for N:
= Total requirement for component N - Number of units of component N on hand
= 320 units - 50 units
= 270 units