All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:
a. adding a significant buffer to each activity
b. be sure to consider learning curves, interruptions and competing priorities
c. estimate times of completion without initial reference to a calendar
d. verify the time estimates with the people doing the work

Respuesta :

oyejam

Answer:

Correct answer is (a). adding a significant buffer to each activity

Explanation:

Realistic time estimates for project is an essential skill required by project management team to estimate required time for a component or whole project to be completed. It is expressed in person hour. Adding a significant buffer to each activity in project management does not required by team to estimate the time required to complete project.