Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in which processes?
1. executing
2. closing
3. initiating
4. monitoring and controlling

Respuesta :

Answer:

2. closing

Explanation:

Closing process is the ending process in any project.

The closing process involved the following activities such as:

Archiving project files - This helps in keeping up of records and statement which can be further used for the similar type of project so as to ease out the project.

closing out contracts - closing of the various contracts that has been issued for the project