Answer:
Option (C) $14,040
Explanation:
Data provided in the question:
Internal rate of return = 12%
Annual rate of return = 18% = 0.18
Cost of the project = $150,000
Salvage value = $6,000
Now,
Annual return = ( Expected net income ) ÷ ( Average investment )
or
Expected net income = Annual return × Average investment
= 0.18 × [ ( Cost of the project + Salvage value ) ÷ 2 ]
= 0.18 × [ ( $150,000 + $6,00 ) ÷ 2 ]
= 0.18 × $78,000
= $14,040
Option (C) $14,040