Answer:
activity 3 rate = $105
Explanation:
Activity 3 $ 52,500 400 100 500
To know the rate we will do
[tex]\frac{Activity\: Cost \: Pool}{Activity}= Activity\:Rate[/tex]
In this case:
cost pool = 52,500
activity = 500
rate = 52,500 / 500 = 105
Then we do:
Product A level x rate = applied overhead
400 x 105 = 42,000
Product B level x rate = applied overhead
100 x 105 = 10,500