Susanne and her team are going to undertake management of a lake. The lake is severely impacted by pollutants from a nearby factory. The team believes that, during the management process, they will have to face undefined issues. If they are beginning to understand the nature of the project, the team is in which stage of adaptive management?

A. Design
B. Implement
C. Monitor
D. Assess

Respuesta :

The correct answer is option D

If the team is beginning to have a grasp of the nature of the project, they are in the ASSESS stage of adaptive management. It is after this stage that they will go ahead to design a strategy which would be implemented. Subsequently, the implemented project will be monitored for proper evaluation and review.

Answer:

D assess

Explanation: