Respuesta :
The answer for this question is D. Project 2; because the present value of the cash inflows exceeds those of Project 1 by $18,598.33
Explanation:
Project 1: You find the factor in the PV(annuity) table corresponding to rate = 15% and time periods = 6. That factor is 3.784. Multiply by the amount of annual cash inflow:
Net Present Value (Project 1) = (3.784 x $52,000) = $ 196,768
Project 2: You find the factor in the PV(annuity) table corresponding to rate = 15% and time periods = 8. That factor is 4.487.
Net Present Value (Project 2) = (4.487 x $48,000) = $ 215,376
So Project 2 should be correct because it has the higher present value
Explanation:
Project 1: You find the factor in the PV(annuity) table corresponding to rate = 15% and time periods = 6. That factor is 3.784. Multiply by the amount of annual cash inflow:
Net Present Value (Project 1) = (3.784 x $52,000) = $ 196,768
Project 2: You find the factor in the PV(annuity) table corresponding to rate = 15% and time periods = 8. That factor is 4.487.
Net Present Value (Project 2) = (4.487 x $48,000) = $ 215,376
So Project 2 should be correct because it has the higher present value
Answer:
The answer is " project 2, because the present value of the cash inflows exceeds those of project 1 by $18,598.33"
Explanation:
As the two projects are mutually exclusive ( must choose one of them, instead of two); the project with higher net present value will be chosen.
We have:
* Net present value of project 1 = (52,000/0.15) * [1 - 1.15^(-6)] - startup cost = 196,793.10 - startup cost;
* Net present value of project 2 = (48,000/0.15) * [1 - 1.15^(-8)] - startup cost = 215,391.43 - startup cost.
=> The difference between NPV of Project 2 and NPV of Project 1 is: 215,391 - startup cost - 196,793 + startup cost = $18,598.33
=> The right choice is: "project 2, because the present value of the cash inflows exceeds those of project 1 by $18,598.33"