A production line is to be designed for a job with three tasks. the task times are 0.4 minutes, 1.2 minutes, and 0.5 minutes. the maximum cycle time in minutes is:

Respuesta :

Durant missed the preseason finale against Sacramento, allowing Nick Young to get experience starting and score 15 points.

Based on the information given the maximum cycle time in minutes is: 2.1.

Maximum cycle time:

To find the maximum cycle time we would have to sum up all the task times or add up all the tasks times.

The task time are: 0.4 minutes, 1.2 minutes, and 0.5 minutes

Hence:

Maximum cycle time=0.4 minutes+ 1.2 minutes+ 0.5 minutes

Maximum cycle time=2.1 minutes

Inconclusion the maximum cycle time in minutes is: 2.1.