63 / 9 = 7
7 / 4 = 1.75
It takes 1.75 minutes for 1 person to paint 1 wall...
1.75 * 4 = 7
7 * 7 = 49
It took 49 minutes for 7 people to paint 4 walls...

Answer:

7 people will take 16 minutes to paint 4 walls.

Step-by-step explanation:

Since, if [tex]x_1[/tex] people take [tex]n_1[/tex] times for [tex]w_1[/tex] work and in the same kind of work [tex]x_2[/tex] people take [tex]n_2[/tex] time for [tex]w_2[/tex] work,

Then,

[tex]\frac{x_1\times n_1}{w_1}=\frac{x_2\times n_2}{w_2}[/tex]

Here, [tex]x_1=4[/tex], [tex]n_1=63[/tex], [tex]w_1=9[/tex],

[tex]x_2=7[/tex], [tex]w_2=4[/tex]

By substituting the values in the above formula,

[tex]\frac{4\times 63}{9}=\frac{7n_2}{4}[/tex]

By the cross multiplication,

[tex]1008=63n_2[/tex]

[tex]\implies n_2=\frac{1008}{63}=16[/tex]

Hence, 7 people will take 16 minutes to paint 4 walls.