Exercise 17-2 (Algo) Computing plantwide overhead rate LO P1 Hydro Sports budgets overhead cost of $440,000 for the year. The company manufactures two types of jet skis: standard and deluxe. Budgeted direct labor hours per unit are 7 for the standard model and 13 for the deluxe model. The company budgets production of 110 units of the standard model and 110 units of the deluxe model for the year. 1. Compute the total number of budgeted direct labor hours for the year. 2. Compute the plantwide overhead rate using budgeted direct labor hours. 3. Compute overhead cost per unit for each model using the plantwide overhead rate. Actual direct labor hours per unit are 7 for the standard model and 13 for the deluxe model.

Respuesta :

To solve this problem, we’ll go through each step, calculating the required values.

Step 1: Compute the total number of budgeted direct labor hours for the year.

For the standard model:

• Direct labor hours per unit = 7 hours
• Budgeted production = 110 units

Total direct labor hours for standard model = (7 \text{ hours/unit}⬤