Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in less than 100 days?
Options:
A) 0.25
B) 0.50
C) 0.75
D) 1.00