1. We are tracking the performance of three of the tasks on your project: Task one involves 40 labour hours per week at an average loaded labour rate of R20 per hour per person. There are 5 people working on task one. Due to the nationwide transport strike, they are performing at 100%, 100%, 80%, 60% and 30% of their capacity respectively. Task two involves 100 hours per week of labour at R250 per hour for one consultant working at 100% of her capacity. Task three involves three people each working 60 hours per week at 100% capacity and respectively earning R50, R80 and R100 per hour. Calculate:
c) Actual cost (AC) for each task individually and for the combined tasks ​