please refer to the following process consisting of five machines producing a metal part. the parts move from machine to machine in the sequence shown. the time each machine takes to work on the part is also shown. which machine in this process is the bottleneck machine?CAN ASK THIS QUESTION AS TEXT WITHOUT INCLUDING DIAGRAM OF THE SEQUENCE:
A process consists of five machines producing a metal part. The parts move in sequence from Machine 1 to Machine 5. Processing at Machine 1 takes 10 seconds then the parts move to Machine 2 where processing takes 15 seconds. In Machine 3, the processing takes 12 seconds and in Machine 4, the processing takes 20 seconds. The parts finally move to Machine 5 where processing takes 18 seconds. Which machine in this process is the bottleneck machine?
a. Machine 1
b. Machine 2
c. Machine 3
d. Machine 4
e. Machine 5

Respuesta :

Based on the discussion, Machine 4 does have the longest processing (20 seconds). As a result, Machine-4 is the process's bottleneck.

What is a machine, and what are some examples?

A device is a hardware device that does active work. This is in contrast to an entity that performs work passively, such as a drainpipe. A machine consumes power but is not always electrical. Machines, for example, can be powered by breeze, water, thermal, chemical, or human power.

What are the five most important simple machines?

The wheel and axle, the pulley, predisposed plane, screw, wedge, and lever are examples of simple computers that are widely used.

To know more about Machine visit:

https://brainly.com/question/15287932

#SPJ4