The critical path for the network would be given as: D. 1-3—4—7. Option D
The project network activity sequence that results in the longest total duration, whether or not that greatest duration includes float, is referred to as a key path in project management. This establishes the quickest timeframe for the project's completion. The critical path may have "total float" (unused time).
Create a schedule network diagram to show the relationships between your tasks. To determine the time required to finish each path, identify all potential routes through the diagram and total up the times required for all jobs. Your critical path is the one with the longest overall duration.
Read more on critical path here:https://brainly.com/question/15091786