You're concerned that inexperienced people on your team might be running behind schedule on their assignments. you decide to apply the Slipped late progress filter to display tasks that are behind in both finish date and completed work.
Slipped Late Progress filter is used in the given situation
The Slipped/Late Progress filter allows the user in seeing tasks which have been slipped behind their scheduled finish date or they haven't been progressing as scheduled by the user.
In order to apply the “Slipped/Late Progress” filter,
first go to menu Project – Filter and
then select More Filters
then again select Slipped/Late Progress
and finally click on Apply button.
To know more about slipped late progress filter here: