You're concerned that inexperienced people on your team might be running behind schedule on their assignments. you decide to apply the _____ filter to display tasks that are behind in both finish date and completed work.

Respuesta :

You're concerned that inexperienced people on your team might be running behind schedule on their assignments. you decide to apply the Slipped late progress filter to display tasks that are behind in both finish date and completed work.

Slipped Late Progress filter is used in the given situation

The Slipped/Late Progress filter allows the user in  seeing tasks which  have been  slipped behind their scheduled finish date or they haven't been progressing as scheduled by the user.

In order to apply the “Slipped/Late Progress” filter,

first go to menu Project – Filter and

then select More Filters

then again select Slipped/Late Progress

and finally click on Apply button.