In a process with rework, we find the bottleneck as the resource with the highest implied utilization.
The given statement is True
What is bottleneck process?
Products are usually produced through a lot of processes in a factory, but takes a lot of time and cost to plan the capacities for all processes. Bottleneck process refers to the process where products that require focused plans and controls are manufactured, and includes the processes requiring the machine/equipment whose quantity is limited, mold tool, and special skills. It makes the control more effective than across-the-board control to intensively control these processes by setting them as bottleneck process.
To learn more about bottleneck process, refer to:
brainly.com/question/13302820