contestada

In the context of earned value management, ____ are calculated by subtracting the actual cost or planned value from ev, and indexes are calculated by dividing ev by the actual cost or planned value.

Respuesta :

In the context of earned value management, variances are calculated by subtracting the actual cost or planned value from ev, and indexes are calculated by dividing ev by the actual cost or planned value. In order to monitor progress against a baseline, identify problems, and anticipate cost (and, to some extent, schedule) upon completion.

Earned Value Management (EVM), a project performance management methodology, integrates cost, schedule, technical scope, and risk. Earned value can be calculated as follows: Earned Value is calculated as Task Budget x Actual Percent Complete the context of earned value management, variances are calculated by subtracting the actual cost or planned value from ev.

To learn more about earned value, click here.

https://brainly.com/question/14897235

#SPJ4