The direct result of disaggregating the aggregate plan is the Multiple Choice marketing plan. production plan. material requirements plan. rough-cut capacity plan. master schedule.

Respuesta :

Master Schedule is the direct result of disaggregating the aggregate plan to identify the timeframe of individual items ahead of time.

What is disaggregating of aggregate planning?

Disaggregating an aggregate plan entails disintegrating or breakdown of an aggregate plan into individual product specifications in order to assess labor ( size, workforce, or skills), resources, and inventory needs.

The aggregate plan is disaggregated into a master schedule, which displays the amount and timing of individual end items over a projected timeframe of roughly 6 - 8  weeks ahead.