The weekly cost per worker is: $800
Unit rate can be used for calculating expenses, calculating cost of multiple units, or calculating expenses.
Recall:
Unit rate is calculated using: [tex]\mathbf{\frac{y_2 - y_1}{x_2 - x_1} }[/tex]
Unit rate represents the amount of a quantity compared to its unit of measure.
Unit rate can be used for calculating expenses, calculating cost of multiple units, or calculating expenses.
Since the relationship between number of workers and weekly cost is proportional, we would apply [tex]\mathbf{\frac{y_2 - y_1}{x_2 - x_1} }[/tex] in determining the weekly cost per worker using the points, (6, 4800) and (15, 12000):
Unit rate/weekly cost per worker = [tex]\frac{12,000 - 4,800}{15 - 6} = \frac{7,200}{9} = 800[/tex]
Unit rate/weekly cost per worker = $800
In summary, the weekly cost per worker is: $800
Unit rate can be used for calculating expenses, calculating cost of multiple units, or calculating expenses.