Select the correct answer.
Which statement is true with regard to project scheduling?
O A. Scheduling in plan-based processes does not change with the progress of the project.
B.
Plan-based processes use an iterative approach for scheduling each phase of the project.
O c.
Scheduling in an agile process involves planning the short-term phases of a project.
OD
Agile processes require less detail than plan-based processes do in an initial project schedule.