Answer:
$7.50 per machine hour
Explanation:
Calculation to determine what The contribution margin per machine hour for Floor Deodorizer is:
First step is to calculate the CM
CM = $13 – 10
CM= $3/ unit
Second step is to calculate Hours/ unit
Hours/ unit= 2,000 / 5,000
Hours/ unit= 0.4 hours
Now calculate the contribution margin per machine hour
Contribution margin per machine hour=$3/ 0.4 hours
Contribution margin per machine hour= $7.50 per machine hour
Therefore The contribution margin per machine hour for Floor Deodorizer is:$7.50 per machine hour