Amir has 103 days to finsih project he works 7 days a week on the project how many week and days does amir have to finish the project

Respuesta :

Answer: 14 weeks 5 days

Step-by-step explanation:

From the question, we are informed that Amir has 103 days to finish a project and that he works 7 days a week on the project.

The number of weeks and days that he has to finish the project will be:

= 103/7

= 14 5/7

= 14 weeks 5 days