Answer:
y = 7.678X + 357.614 ;
518.852 ; 526.53 ;
Week 78;
Explanation:
Given the data :
Week Number Week Number Week Number
1 370 7 415 13 450
2 380 8 425 14 455
3 390 9 435 15 475
4 380 10 425 16 485
5 390 11 435 17 495
6 395 12 445 18 505
The linear trend line for expected freight car loading obtained using a linear model calculator is :
y = 7.678X + 357.614
y = expected freight car loading
X = week
m = slope = 7.678 ;
c = intercept = 357.614
B.)
predicted loading for week 21:
X = 21
y = 7.678(21) + 357.614 = 518.852
Predicted loading for week 22:
y = 7.678(22) + 357.614 = 526.53
C.)
Week loading volume should exceed 950:
y = 950
950 = 7.678X + 357.614
950 - 357.614 = 7.678X
592.386 = 7.678X
X = 592.386 / 7.678
X = 77.153685
X = 78 (should exceed 950)