Bettendorf Corporation uses a job order costing system. The plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. Job B-600 has the following cost information: Direct materials $ 210 Direct labor $ 180 Required: 1. What is the total manufacturing cost assigned to Job B-600

Respuesta :

Answer:

Missing word " 2. If Job B-600 consists of BO units, what is the unit product cost for this job?"

1. Particulars                          Amount

Direct Materials                    $210

Direct Labor                          $180

Plantwide overheads           $315

Total manufacturing cost   $705

Labor hour rate is $12 per hour

Hence, total labor hours = $180/$12 = 15 hours

Total plantwide overheads = $21 * 15 =$315

2. Particulars                          Amount

Direct Materials                    $210

Direct Labor                          $180

Plantwide overheads           $315

Total manufacturing cost   $705

Total unit                                80  

Cost per unit                        $8.813