Answer:
The right answer is "$14,496".
Explanation:
The given values are:
Direct material cost,
= $7700
Labor hours,
= 178
Wage rate,
= $22 per hour
Machine hours,
= 90
Predetermined overhead rate per machine,
= $32
Now,
The direct labors cost will be:
= [tex]Labor \ hours\times wage \ rate[/tex]
= [tex]178\times 22[/tex]
= [tex]3,916[/tex] ($)
Mfg. overhead costs will be:
= [tex]Machine \ hours\times Predetermined \ overhead \ rate[/tex]
= [tex]90\times 32[/tex]
= [tex]2,880[/tex] ($)
So,
The total manufacturing cost will be:
= [tex]7700+3916+2880[/tex]
= [tex]14,496[/tex] ($)