The expected completion time of the project is:
10 days.
Step-by-step explanation:
Duration of Task A = 5 days
Task B and C depend on Task A
This implies that Task A must be completed before Task B and C can be started.
To complete Task B will take 5 days
To complete Task C will take 5 days (7 * 0.5) + (3 * 0.5)
Since Task A takes 5 days and Tasks B and C depend on Task A and Task B takes 5 days and Task C takes expected time of 5 days, it means that the project can be completed in 10 days (5 + 5) if tasks B and C are simultaneously carried out.
The expected completion time of the project is
(i)10 days if B&C are mutually independent
(ii)15 days if B &C are mutually dependent
What is the expected completion time of a task?
Expected completion time of a task= p1x1 + p2x2
Where
p1 & p2 are probabilities.
x1 and x2 are samples.
p1=p2=0.5
x1=7
x2=3
Expected completion time of task C= 0.5*7+0.5*3 = 5 days
Task B and C will be due till task A is not accomplished.
Total time to accomplish task A = 5 days
Total time to accomplish task B= 5 days
Expected time to accomplish task C = 5 days
If tasks B and C are mutually independent
expected time to complete the project = 5+5=10days
If task C depends on task B
Expected time to complete the project = 5+5+5 = 15 days.
Therefore
The expected completion time of the project is
(i)10 days if B&C are mutually independent
(ii)15 days if B and C are mutually dependent