Variable manufacturing overhead spending variance= $2,000 favorable
Explanation:
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 2,400,000 / 240,000
Predetermined manufacturing overhead rate= $10 per machine hour
To calculate the variable overhead spending variance, we need to use the following formula:
Variable manufacturing overhead spending variance= (standard rate - actual rate)* actual quantity
Variable manufacturing overhead spending variance= (15 - 214,000/21,600)*21,600
Variable manufacturing overhead spending variance= $2,000 favorable
The Nanjones' variable overhead spending variance for November is a. $6,000 favorable.
Data and Calculations:
Planning Data Actual Data Variances
Annual November November
Fixed overhead $1,200,000 $100,000 $101,200 $1,200 U
Variable overhead $2,400,000 $220,000 $214,000 $6,000 F
Direct labor hours 48,000 4,000 4,200 200 U
Machine hours 240,000 22,000 21,600 400 F
Thus, the Nanjones' variable overhead spending variance for November is the difference between planned expenses and actual expenses, which is $6,000 ($214,000 - $220,000) favorable.