Answer:
$12000 ( A )
Explanation:
Calculate The minimum cost to crash this project by 2 weeks
To get the minimum cost to crash this project in 2 weeks we have to first look to crash the activity on the critical path that has the lowest cost of crashing from the first week
critical path: A-B-D-F-G = 25 weeks
After crashing Activity B by 1 week both paths become critical paths hence we need to crash activity C and D by 1 week each so that the paths can crash simultaneously within 2 weeks
therefore the overall crash cost for 2 weeks will be
crash costs of Activities : B + C + D ( 1st crashes)
= 3500 + 4000 + 4500
= $12000