Answer:
Predetermined manufacturing overhead rate= $53,75 per machine hour
Explanation:
Giving the following information:
Order size:
Estimated activity cost= $585,866
Estimated machine hours= 10,900
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 585,866/10,900
Predetermined manufacturing overhead rate= $53,75 per machine hour