a. Journal entries
Dec. 2
Raw Materials $400,000 (debit)
Accounts Payable $400,000 (credit)
Dec. 3
Work In Process : job no. 100 $100,000 (debit)
Raw Materials $100,000 (credit)
Dec. 9
Work In Process : job no. 101 $150,000 (debit)
Raw Materials $150,000 (credit)
Dec. 15
Work In Process : job no. 102 $30,000 (debit)
Raw Materials $30,000 (credit)
Dec. 28
Work In Process : job no. 100 $9,000 (debit)
Work In Process : job no. 101 $11,000 (debit)
Work In Process : job no. 102 $5,000 (debit)
Salaries Payable $100,000 (credit)
Dec. 28
Work In Process : job no. 100 $27,000 (debit)
Work In Process : job no. 101 $33,000 (debit)
Work In Process : job no. 102 $15,000 (debit)
Overheads $75,000 (credit)
Dec. 29
Finished Goods : job no. 100 $136,000 (debit)
Finished Goods : job no. 101 $194,000 (debit)
Work In Process : job no. 100 $136,000 (credit)
Work In Process : job no. 101 $194,000 (credit)
Dec. 30
Accounts Receivable $200,000 (debit)
Cost of Sales : job no. 100 $136,000 (debit)
Sales Revenue $200,000 (credit)
Finished Goods : job no. 100 $136,000 (credit)
Dec. 31
Overheads $78,000 (debit)
Cash $78,000 (credit)
Dec. 31
Cost of Sales $3,000 (debit)
Overheads $3,000 (credit)
b. Cost of Goods Sold
Cost of Sales : job no. 100 $136,000
Add Under - Applied Overheads $3,000
Cost of Goods Sold $139,000
c. inventory balances
Work In Process Balance $50,000
Finished Goods Balance $194,000
Raw Materials Balance $120,000
d. Manufacturing Overheads Application
Manufacturing Overheads were under-applied by $3,000
Explanation:
Raw Materials Balance :
Raw Materials Purchase $400,000
Less Materials Used
job no. 100 ($100,000)
job no. 101 ($150,000)
job no. 102 ($30,000)
Raw Materials Balance $120,000
Work In Process Balance :
Only job no. 102 was yet to be completed
Costs of this job is as follows :
Raw Materials $30,000
Direct Labor $5,000
Overheads $15,000
Work In Process Balance $50,000
Finished Goods Balances :
Only Job 101 was completed and yet to be sold
Raw Materials $150,000
Direct Labor $11,000
Overheads $33,000
Finished Goods Balance $194,000