Answer:
Explanation:
Direct material cost per equivalent unit = Cost of direct materials transferred in/ Equivalent units for direct materials
= 588,000/3,000
= $196 per ton
Conversion Cost per equivalent unit = Conversion cost for the period / Conversion cost per equivalent
= 296,400/5,200
= $57 per ton