The earliest time that an activity can be completed is equal to the latest time it can begin minus the time to perform the activity. Group of answer choices True False

Respuesta :

Answer: False

Explanation:

The earliest time of an activity os necessary in order to reduce the duration of a project. The earliest start time of an activity is the time that is earliest where an activity can begin.

The earliest finish time is the addition of the early time with the completion time of the activity.