Answer:
The standard hours allowed for May production would be 2,250 hours
Explanation:
In order to calculate the standard hours allowed for May production we would have to calculate the following formula:
Standard Hours allowed = actual Units / Budgeted units * Budgeted Labour Hours
actual Units=900
Budgeted units=1,000
Budgeted Labour Hours=2,5000 hours
Therefore, Standard Hours allowed =900/1,000 * 2,500 = 2,250 Hours
Standard Hours allowed = 2,250 Hours
The standard hours allowed for May production would be 2,250 hours