Answer:
Explanation:
Reorder point quantity is the level at which an inventory is expected to be restocked , calculated by finding the sum of demand over the lead time and the safety stock days
Daily usage = 800 feet / day
Lead time = 6 days
Desired service level = 95%
Risk level = 1-0.95 =0.05
safety stock at 0.05 = 1800
Reorder point = expected demand in (LT) + safety stock
= (800*6) + 1800
= 4800+1800 = 6600 feet.