Answer:
The total cost of the units started and completed during the period is $181,306. The right answer is b
Explanation:
In order to calculate the total cost of the units started and completed during the period we would have to calculate the Equivalent units as follows:
Equivalent units:
Whole units material conversion
Beginning units 2,400 0 1,800(75%)
Units started and complete 10,900 10,900 10,900
(13,300-2,400)
Total transferred 13,300 10,900 $ 12,700
Ending units 20,00 2,000 400(20%)
Equivalent units 15,300 12,900 13,100
Equivalent cost per unit:
Material conversion
Cost incurred this period $116,100 $100,000
÷ equivalent units ×12,900 ÷13,100
Cost per equivalent unit $9 $7.6336
Therefore, the total cost of the units started and completed during the period =10,900 units×($9+7.6336)
=$181,306