Respuesta :
Answer:
Therefore, The activity variance for catering supplies in July would be closest to 101 favorable
Explanation:
In order to to calculate the The activity variance for catering supplies in July we would need to calculate the Budgeted Value and the Actual Value as follows:
Budgeted Value = 350 + 15 * 84 + 127 * 17 = $3,769
Actual Value = 350 + 14*84 + 126 * 17 = $3,668
Since Actual Value is less than Budgeted Value, there will be a favorable variance of 101.
Therefore, The activity variance for catering supplies in July would be closest to 101 favorable
Answer:
Activity variance $109 favorable
Explanation:
The activity variance occurs as result of the difference between the actual level of work (activity) done and the budgeted level of work as planned.
$
Budgeted cost for the planned activity
= $310 + ( $85 × 15) + ($17×127) 3,729
Actual cost = 3,620
Activity variance 109 favorable
Activity variance $109 favorable