Assume the​ following: ​WIP, beginning 2 comma 500 units​ (100% complete as to direct​ materials, 50​% complete as to conversion​ costs) Started 10 comma 500 units during the period Total spoilage is 700 with normal spoilage is calculated to be 550 units Completed and transferred out during the period 6 comma 000 units ​WIP, ending 6 comma 300 units​ (100% complete as to direct​ materials, 60​% complete as to conversion​ costs) Spoiled units 700 and inspection happens when the process is 20​% complete All materials are added at the start of the process Under the weighted average​ method, would would be the equivalent units of work done for the​ period? A. 9 comma 920 B. 10 comma 190 C. 6 comma 000 D. 6 comma 300

Respuesta :

Answer:

B. 10 comma 190

Or none of the given

Explanation:

Particulars         Units       % of Completion         Equivalent Units

                                   Materials Conversion     Materials    Conversion

Transferred       6000         100       100              6000        6000

+Ending WIP       6300         100        60               6300        3780

+Normal Spoilage 550         100        60               550           330

+Abnormal

Spoilage              150          100        60            150               90      

Total                                                                    13000          10200

As we see the total  weighted Equivalent units  for materials are 13000

and for conversion are 10200 . So the correct choice would be 10190 that is choice B which the nearest answer of the choices given to the answer calculated .

Under weighted method the Transferred out units are added to the ending work in process and the normal and abnormal spoilage is also added to find the equivalent units of production.

The other answer would be none of the given choices if exact figures are to be matched.