Answer:
6.00 days
Explanation:
data provided
Inspection time = 3.7 days
Process time = 0.2 days
Move time = 1.3 days
Queue time = 0.8 days
The calculation of throughput time is given below:-
Throughput time = Inspection time + Process time + Move time + Queue time
= 3.7 days + 0.2 days + 1.3 days + 0.8 days
= 6.00 days
Here, we added the inspection time, process time , move time and queue time to reach at throughput time and we ignore the time spent waiting to be worked on in the factory as it is not relevant.