Answer:
Project S = $672.48
Project L = $11,500
Explanation:
Net Present Value (NPV) Is Calculated by Taking the Present day (Discounted) Value of all future Net Cash flows based on the Business Cost of Capital and Subtracting the Initial Cost of the Investment.
Using a Financial Calculator NPV calculations will be as follows:
Project S
CF0 = ( $11,000)
CF1 = $3,400
CF2 = $3,400
CF3 = $3,400
CF4 = $3,400
CF5 = $3,400
i = 14 %
NPV = $672.48
Project L
CF0 = ( $23,000)
CF1 = $6,900
CF2 = $6,900
CF3 = $6,900
CF4 = $6,900
CF5 = $6,900
i = 14 %
NPV = $11,500.