If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation, z-value to 2 decimal places and Probability to 4 decimal places.) Path Mean Std. Dev. a-d-e-h 24.33 1.35 a-f-g 15.50 1.26 b-i-j-k 14.83 1.02 c-m-n-o 26.17 1.66 Probability ($1,000) .4099 Probability ($500)