Answer:
CPI= 1.25 THE PROJECT FINANCE PERFORMANCE IS GOOD SO FAR
Explanation:
To know the efficiency of the use of financial resources in the project so far we need to know the Cost Performance Index (CPI)
CPI =EV/AC
EV =$50,000
AC=$40,000
CPI =$50000/$40000
CPI = 1.25
So for every dollar you use 1.25 dollars is made this means the project so far is a efficient