An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity

Respuesta :

The expected duration of the activity is 29 days and 4 hours.

Step-by-step explanation:

Step 1:

The optimistic time, [tex]t_{o}[/tex] = 25 days,

The most likely estimate, [tex]t_{m}[/tex] = 29 days.

The pessimistic time, [tex]t_{p}[/tex] = 34 days.

According to PERT, the expected duration of the activity, [tex]t_{e} = \frac{t_{0}+4t_{m} +t_{p} }{6}.[/tex]

Step 2:

By substituting the given values, we get[tex]t_{e} = \frac{t_{0}+4t_{m} +t_{p} }{6} = t_{e} = \frac{25+4(29) +34 }{6} = \frac{175}{6} = 29.1666.[/tex]

0.1666 days = [tex]0.1666 (24) = 3.9999 hours.[/tex]

29.1666 days approximately equal 29 days and 4 hours.