Which of the followings is true: a) the WBS is the basis for project schedules, budgets, and controls. b) work packages are the basis for project schedules, budgets, and control. c) project schedules are the basis for work definition. d) both a and b

Respuesta :

Answer:

Option D; both options A and B.

a) THE WBS IS THE BASIS FOR PROJECT SCHEDULES, BUDGETS, AND CONTROLS.

b) WORK PACKAGES ARE THE BASIS FOR PROJECT SCHEDULES, BUDGETS, AND CONTROL.

Explanation:

A work breakdown structure (WBS) is a visual tool for defining and tracking a project deliverable and all the small components needed to create it.

A work-breakdown structure (WBS) in project management and systems engineering, is deliverable oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. It is a basis for project scheduling, cost control, and project budget.

Therefore, both options A and B are true;a) THE WBS IS THE BASIS FOR PROJECT SCHEDULES, BUDGETS, AND CONTROLS.

b) WORK PACKAGES ARE THE BASIS FOR PROJECT SCHEDULES, BUDGETS, AND CONTROL.