Answer:
D. $ 367.500
Explanation:
We have to first compute the total direct labor cost. This is done by multiplying the estimated direct labor hours with the hourly rate.
Total Direct Labour costs $ 17.50 per hour * 15,000 hours = $ 262,500
Estimated manufacturing overhead per the data in the question is 140 % of Direct labor cost,
Estimated manufacturing overhead is $ 262,500 * 140 % = $ 367,500