Answer:
Overhead Cost - S1 = $30201
Explanation:
To assign Overhead costs to S1, we first need to calculate the Overhead Absorption rate for Machining and Order filling.
The Overhead Absorption rate for Machining is calculated by dividing the Machining Overheads by the number of Machine hours to calculate $ Overhead per Machine Hour.
Now we do the same calculation for Order Filling Overheads and divide them by Number of Orders.
Now we allocate the Overheads to S1 on the basis of Machine Hours and Number of orders relating to S1.