Answer:
d. $80 per machine hours
Explanation:
The computation of the overhead rate is shown below:
Overhead rate = Estimated total overhead cost ÷ total machine hours
= $16,000,000 ÷ 200,000 hours
= $80 per machine hours
The overhead rate is come by dividing the estimated total overhead rate by the total machine hours
All the other information that is mentioned is not considered. Hence, ignored it