Jasper Carts manufactures custom carts for a variety of uses. The following data have been recorded for Job​ 651, which was recently completed. Direct materials used cost​ $7,700. There were 178 direct labor hours worked on this job at a direct labor wage rate of​ $22 per hour. There were 90 machine hours used on this job. The predetermined overhead rate is​ $32 per machine hour used.
What is the total manufacturing cost of Job 651?
A) $7,457
B) $13,510
C) $2,460
D) $3,850

Respuesta :

Answer:

$14,496

Explanation:

The computation of the total manufacturing cost of Job 651 is shown below:

= Direct material cost + Direct Labor cost + manufacturing overhead cost

where

Direct material cost is $7,700

Direct Labor cost =  178 direct labor hours × $22 = $3,916

And. the machine hour cost is

= 90 machine hours × $32

= $2,880

So, the total manufacturing cost is

= $7,700 + $3,916 + $2,880

= $14,496

Note: This is the answer but the same is not provided