The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?a. fast-track
b. assign more experienced people to tasks on the critical path
c. crash the schedule
d. cut scope

Respuesta :

Answer:

The correct option is C

Explanation:

Crashing the schedule states or define as to throw or have the extra resources to the critical or vital path without getting the highest efficiency level. It is another schedule which a technique or tool of compression where the person add extra or additional resources to the project in order to compress the schedule.

Under this case, the technique which is followed in order to shorten the project is the crashing the schedule.