Answer:
B. 20
Explanation:
We are given the low and high option
If we do the average we get:
(15 + 25) / 2 = 20
Also, this is a given already Maurice estimates the most likely duration to be 20 days.
Below that should be a good result while above that; there were deficiencies in the scheduling and process which should be evaluate for future task.